Queen Mary Reservoir Isolation Plate Installation

Isolation plate being lifted on a pontoon-mounted A-frame at Queen Mary Reservoir, ready to lower to MMP's divers

As part of the AMP8 works at Queen Mary Reservoir, MMP’s commercial diving team installed seven isolation plates inside the reservoir tower at a water depth of 16 metres.

Pontoon lifting and underwater installation

Using a pontoon-mounted A-frame, the surface team lowered each plate to the divers, who positioned it precisely over its opening. The divers then used specialist underwater tooling, including hydraulic drilling equipment, to secure each plate in place.

Careful planning and close coordination between the surface and diving teams kept every lift controlled and the installation safe throughout.

Solving an unexpected problem on site

During the works, the team found an existing valve that was letting water pass through and needed to be removed. MMP worked closely with the client to assess the problem and adapt the installation sequence, resolving the issue while keeping the programme on track.

Project outcome

All seven isolation plates were successfully installed. The project shows how MMP combines specialist diving with practical problem-solving and a responsive approach when site conditions change.

Services provided

  • Commercial diving at 16 metres

  • Underwater isolation plate installation

  • Pontoon-mounted A-frame lifting operations

  • Hydraulic underwater drilling

  • Valve assessment and removal

Read more about our underwater inspection work, or contact us or call 01992 618055 to discuss your reservoir project.